Upper-level management must decide between pure, functional, and matrix structures as ways to organize projects.

A) True
B) False

Correct Answer

verifed

verified

One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project.

A) True
B) False

Correct Answer

verifed

verified

Earned value management (EVM) has the capability to combine measurements of scope, schedule, and cost in a project.

A) True
B) False

Correct Answer

verifed

verified

A simple project listing of five activities and their respective time estimates are presented here: Using CPM, which activities make up the critical path?


A) A, C, D, E
B) A, B, D, E
C) A, C, B, D, E
D) A, D, E
E) None of these

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A project milestone is a specific event to be reached by a particular point in time.

A) True
B) False

Correct Answer

verifed

verified

Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.

A) True
B) False

Correct Answer

verifed

verified

Some of the advantages of a functional project where the project is housed in a functional division include which of the following?


A) The project manager has full authority over the project.
B) Team pride, motivation, and commitment are high.
C) A team member can work on several projects.
D) Needs of the client are secondary.
E) None of these

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

You have just used the network planning model and found the critical path length is 60 days and there are two critical paths.The standard deviation of the first critical path is 10 days and the s.d.of the second critical path is 15 days.The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy)


A) 0.84
B) B.0.25.
C) 0.16
D) 0.75
E) 0.66.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs.

A) True
B) False

Correct Answer

verifed

verified

You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart.What kind of chart are you looking at?


A) Gantt chart
B) PERT chart
C) Bar/milestone chart
D) Total program cost breakdown
E) EVM chart

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project) ?


A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days

F) A) and C)
G) C) and E)

Correct Answer

verifed

verified

Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.

A) True
B) False

Correct Answer

verifed

verified

You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days.The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy)


A) 0.73
B) 0.55.
C) 0.12
D) 0.27
E) 0.60.

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.

A) True
B) False

Correct Answer

verifed

verified

Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project.

A) True
B) False

Correct Answer

verifed

verified

You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?


A) You have found the critical path.
B) You have run out of crash time.
C) You no longer have a linear relationship with costs.
D) You have reached the minimum total cost.
E) You have run out of crash costs.

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

CPM is an abbreviation for critical path method.

A) True
B) False

Correct Answer

verifed

verified

A matrix project structure is often referred to as a "skunkworks." A pure project is nicknamed skunkworks.

A) True
B) False

Correct Answer

verifed

verified

An event unit package is a subdivision of a project.

A) True
B) False

Correct Answer

verifed

verified

A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.

A) True
B) False

Correct Answer

verifed

verified